|
Phase 1 involved design and construction of four stream barbs
for diverting the channel thalweg away from the bank and an irrigation
inlet. The project also involved biotechnical bank treatments
for mitigation of bank plantings disturbed by construction. Phase
2 involved a conceptual reach study to outline an environmentally
beneficial approach to bank and flood protection issues within
this 5000 foot reach. Future phases are anticipated for designing
and implementing the conceptual solutions proposed in Phase 2.
Metzger
Park Apartments Stream Bank Stabilization Client: Clean Water Services, Washington County, Oregon Completed: 1999
The
foundation of an existing building in the Metzger Park Apartments
was threatened by stream bank erosion of Ash Creek. PWR as subconsultant
to KAI conducted a detailed hydraulic and scour analysis for
both existing and proposed conditions at the site. PWR developed
a bank stabilization design to protect the existing structures.
The design included a stone toe and bioengineered erosion control
for the eroded bank. Armed with the model data PWR developed
several design alternatives for stabilizing this 320-ft. reach.
The work involved stream assessment, wetland delineation,
preliminary and final design drawings, biotechnical bank stabilization,
permit applications and submittals, and County land use submittal.
In addition, the project required a 'no-rise' certification as
all improvements were within the regulatory floodway of Ash Creek.
All design elements considered the no-rise requirement and ultimate
conditions modeling assumed fully mature vegetation and its associated
roughness characteristics. The final design incorporated 180
linear feet of coir lifts, 140 feet of bank regrading, and rock
riprap interplanted with live willow stakes.
Regional
Stormwater Quality Projects Client:
Clean Water Services, Washington County, Oregon; Completed
1996
PWR staff, while working at KAI, led a team of hydrologists,
hydraulic engineers, water quality experts, designers and environmental
scientists to design three regional facilities on Beaverton's
Butternut Creek, Johnson Creek, and Hedges Creek.

The Butternut Creek Water Quality and Detention Facility was
constructed in the summer of 1996. The facility serves to reduce
historical flooding along Butternut Creek by temporarily storing
and very slowly releasing storm water runoff. It will also improve
the water quality of the creek through sedimentation, biofiltration,
and bio-accumulation. This project was identified as a top priority
in CWS' Butternut Creek Subbasin Strategy Plan (developed several
years earlier by PWR staff) to help reduce flooding and improve
water quality in the creek. This project received the 1997 Honor
Award in the 1997 Portland/Vancouver Metropolitan Area Storm
Water Design Award Competition.
In addition to the surface water management benefits, construction
of the Butternut Creek facility enhanced the natural resource
value of the site by replacing mono-typic stands of Reed Canarygrass
and Himalayan Blackberry with native upland and wetland vegetation.
The site contains a diversity of wetland communities with regions
of open water, emergent wetland, wet meadow, and forested wetland
that enhance the wildlife habitat functions of an area that has
been identified as a Significant Natural Resource in the Aloha-Reedville-Cooper
Mountain Community Plan.
The Brookhaven project on Beaverton's Johnson Creek (South)
was constructed as part of the Davis Road improvements. The project
involved the removal of an old beaver dam that had been reinforced
by human intervention. The concern for water temperature violations
in this water quality-limited waterway led to a unique pocket
pond design that required significant regrading and sediment
removal. In addition, an old dry detention basin was retrofitted
to act as an active sediment removal facility for the creek.
As part of the project, the severely eroding stream bank of a
major tributary to Johnson Creek that flowed through the site
was stabilized and restored using bio-engineering techniques.
A severely silted culvert on this tributary was also replaced
by a bridge to relieve local flooding and improve fish passage.
The Hedges Creek project involved a significant amount of
stream bank stabilization using bio-engineering and the retrofit
of a large culvert inlet to provide flood reduction and sediment
removal upstream of the well-known Hedges Creek Marsh. This facility
has not been constructed due to a property dispute with an adjacent
business. |